scanning:5096 author: from: time:2017-10-18 classify:project dynamics
the domestic processing part of the electric bag renovation and new air cooler project of kiln head and kiln tail of kazakhstan 2500td standard cement company has been completed and is ready for shipment

the domestic processing part of the kiln head, kiln tail electric bag replacement and new air cooler projects of kazakhstan's 2500t/d standard cement company has been completed and is ready for shipment.
the project is located in shimkent, a city in southern kazakhstan, 800 kilometers away from the capital and 500 kilometers away from almaty. the project is wholly contracted by tianjin cement design and research institute, and our company is responsible for equipment production and on-site installation. the production part of this project has been processed in china and will be shipped soon.